[12] During the development process, the Developer will advise the PM in a timely fashion of any deviations from the agreed project scope and requirements that may require the PM to raise a change control for the customer.
The customer will be notified of changes in project scope, requirements or specification by the PM completing and sending a ‘Change Control’ document.
Both InfoSys and the customer will be able to raise Change Control documents during the development process.
The ‘Change Control’ document will identify:
- The application’s name
- The application’s version number
- The current state of the element to be changed
- The proposed change itself
- The impact of the change (cost, time & benefits) from p.o.v of the party proposing change
- The parties affected by the change
- The names of the people to review the change control
Each Change Control document will be filed in the ‘Projects’ database.
In the event of a Change Control document being approved by a Customer. The PM will revise the project plan, adjust the cost and advise the customer as appropriate.